Tacquet-Industries

Hot Tapping and Line Plugging 4″

4″ Hot Tapping & Line Plugging

As part of a live water network intervention, we carried out a DN100 PN16 line plugging operation, enabling safe work without interrupting service.

The operation began with the supply and installation of a full-encirclement tapping fitting and a full-bore valve. Once our teams and equipment were mobilized, a controlled under-pressure drilling was performed, preceded by a nitrogen tightness test.

In parallel, a mechanical saddle and a secondary 1″ valve were installed to allow for network purging. A second hot tap was carried out for this purpose.

The line plug was then inserted to isolate the targeted section, allowing downstream work to be conducted under optimal conditions. Continuous monitoring was ensured throughout the plugging phase. At the end of the intervention, the system was safely removed and all components dismantled with care.

This operation reflects our expertise in live network interventions, combining safety, precision, and technical control.

20 march 2025

Machining of rudder stock bearing surface

Machining of Rudder Stock Bearing Surface – MARTINIQUE

A precision machining operation was carried out on the bearing surface of a rudder stock system, as part of a technical intervention conducted in Martinique. The primary objective of this service was to restore the geometrical integrity of the bearing surface to ensure safe and compliant operation.

The intervention was executed in several phases: preparation and setup of the working environment, initial inspection of the affected area, installation of an orbital machining system, alignment based on reference surfaces, and then the actual machining process. A final inspection validated the operation before disassembling the equipment and closing the worksite.

The teams maintained rigorous oversight throughout the operation—from site assessment to the drafting of the final intervention reports. All deployed resources were aimed at ensuring high-quality machining in a demanding technical environment.

This type of service showcases the expertise available for on-site metrology and machining operations, performed under real-world conditions while adhering to industrial standards of safety, cleanliness, and traceability.

March 2025

Metrological control of the fixed parts of the G2

Metrology Inspection of the Fixed Parts of a Vertical Unit


A dimensional inspection was carried out on the fixed parts of unit G2 within an industrial facility, as part of an on-site metrology campaign.

The objective of this mission was to verify the geometric conformity of the fixed structures, which are essential to the stability and proper functioning of the equipment. This type of inspection helps prevent misalignments, ensures mechanical interfaces, and guarantees the quality of assemblies.

Measurements were performed using high-precision instruments, enabling rigorous and representative data collection of the components, in accordance with the site’s technical requirements.

All points outlined in the inspection plan were covered. A comprehensive report was issued at the end of the intervention, serving as a basis for monitoring the condition of the structures and planning any necessary maintenance actions.

This type of service is part of a dimensional control approach and actively contributes to the overall reliability of industrial installations.

Intervention on March 4, 2025

Hot Tap DN65 on DN100 Header

Two DN65 Hot Taps on DN100 Hot Water Header

As part of an intervention on a pressurized hot water network, our teams successfully carried out two DN65 hot taps on a DN100 header, without interrupting service.

Following insulation removal by the client and precise location marking, we installed two mechanical saddles on the cleaned and prepared header.

Each tapping point was fitted with a DN65 PN16 full-bore valve. Our technicians then mounted the drilling machine, followed by a nitrogen tightness test to ensure the system’s integrity.
The under-pressure drilling (Ø 60 mm) was performed with precision, and the coupons were returned to the client.

This operation was completed with the highest level of rigor and in compliance with safety standards, ensuring uninterrupted operation of the network and providing a reliable solution for future tie-ins.

13 febuary 2025

Control geometry Porte Amont

Geometrical Inspection – Porte Amont 

A precision metrology operation was carried out on the upstream gate of the main lock chamber at the EDF hydroelectric site in Marckolsheim, as part of a complete geometrical inspection. The objective was to verify the dimensional integrity of all gate components, both in dry conditions and under operational load.

The inspection focused on several key aspects: flatness of the gate leaves, positioning and behavior of the latching systems (both movable and fixed), and relative displacements of components between different closure configurations. Measurements were performed using a laser tracker, allowing for high-accuracy data acquisition within a complex environment, with alignment based on a reference frame constructed from structural points of the installation.

Specific targets were placed to measure geometric variations across multiple operational states (open/closed, dry/loaded). The intervention also included a study of rotation centers and alignment of critical mechanical components.

All points outlined in the control plan were successfully measured. A technical report, including a 3D model and a comprehensive surface map, was delivered to the site operator for documentation and future analysis.

This type of inspection plays a vital role in the safety and reliability of hydraulic infrastructure, providing a precise and documented assessment of the actual geometrical condition of the structures.

Intervention of February 7, 2025

Hot Taps DN25 on DN700 Header

Six piquages en charge DN25 sur collecteur vapeur DN700

Dans le cadre d’une intervention sur un collecteur de vapeur de grand diamètre, nos équipes ont procédé à la réalisation de six piquages en charge DN25 sur une conduite DN700, en conditions de service. Les piquages, équipés de vannes à passage intégral et de manchons filetés 1″ NPT, ont été préalablement fournis et soudés par le client.

Nos techniciens ont ensuite pris en charge les opérations de forage sous pression. Chaque perçage, réalisé avec précision (Ø 19 mm), a été précédé d’un test d’étanchéité à l’azote afin d’assurer la fiabilité du montage. L’ensemble des opérations a été répété sur les six points de piquage, avec mobilisation maîtrisée de notre machine de forage.

Cette intervention illustre notre capacité à intervenir sur des installations sensibles en environnement vapeur, à haute température, tout en garantissant la continuité de fonctionnement du réseau et le respect des normes de sécurité les plus strictes.

Intervention du 24 janvier 2025

Tracker Laser Calypso

Metrology Inspection by Laser Tracker on a Pelton Unit


As part of an on-site industrial metrology intervention, a dimensional inspection was performed on a Pelton unit, focusing on both the fixed and movable covers, assessed directly in their functional configuration.

The objective of this operation was to verify the geometric conformity of the assembly, ensuring optimal fit between the movable and fixed components, as well as maintaining the stability and precision of the installation.

A high-precision laser tracker was used to carry out the measurements, providing fast and reliable acquisition of geometries, even in constrained environments. The inspection was conducted with the covers held in their actual operational positions, ensuring the relevance of the measurements, and then removed afterward.

The analysis enabled evaluation of clearances, alignments, and geometric consistency between the different components. At the end of the inspection, a detailed report was issued, including measurement data and recommendations for potential adjustments or long-term monitoring.

This type of intervention highlights the value of laser tracker inspections for large structures or complex assemblies and supports dimensional control as a key factor in equipment reliability.

Intervention of 17 January 2025

Rehabilitation of a turbine COO

REHABILITATION OF A TURBINE

A final intervention to finish the year 2024, machining of group 2 of the magnificent Coo Trois-Ponts power plant.

Rehabilitation for a future overpower:
1st step machining of the labyrinth with different bores (about 2500mm diameter) and surface to be realized.
2nd stage machining of the holes at the level of the spiral tarpaulin. (5500mm diameter)

PRE-WORK & MACHINE SETUP

Installation of our machine in the turbine and adjustment with the help of the Laser Tracker

Control and adjustment of the G1 rotor shaft.

Labyrinth Inspection and Adjustment


As part of a technical on-site intervention, a complete metrology inspection was carried out on the fixed parts of unit G1, followed by an adjustment and finishing phase. The operation took place over several days and involved various stages of measurement, machining, and final validation.

The process began with an initial dimensional survey to assess the condition of the component prior to intervention. A machine adjustment phase was then implemented to ensure precise surface preparation before cladding. This was followed by finishing machining operations and a final inspection after surface treatment, all performed in a controlled industrial environment.

Each stage was accompanied by rigorous tracking of geometric references, using a reference system adapted to the functional orientation of the part. A laser tracker measurement system was used to ensure the required precision at every step of the process.

In parallel, a final dimensional inspection was carried out on the entire G1 unit, including checks on critical geometries, assessment of angular positions of drilled holes, and overall validation after machining. All scheduled measurements were completed in accordance with the control plan requirements.

This operation is part of a broader effort to restore technical compliance and secure the mechanical components of the plant, ensuring their optimal integration within the overall system.

Intervention of 20 December 2024

Control the DIM and GEO wheels, Francis.

Geometric and Dimensional Inspection of a Francis Runner

As part of a specialized metrology operation, a comprehensive geometric and dimensional inspection was carried out on a Francis runner, a key component of a hydraulic turbine.

The purpose of this intervention was to verify the conformity of the runner’s surfaces and blades, ensuring adherence to manufacturing tolerances and overall uniformity. These criteria are critical to guarantee hydraulic performance, durability, and optimal balancing during operation.

To meet these requirements, high-precision measuring tools were deployed on-site, including a laser tracker, enabling full coverage of the component’s complex geometry.

Measurements focused on several aspects: blade profile and thickness, geometry of the support surfaces, angular distribution, and analysis of overall shape deviations. All data was compiled into a dedicated report designed to assist technical teams in validating, monitoring, or adjusting the component as needed.

This type of inspection helps secure the assembly or recommissioning phases by providing a reliable and documented database of the runner’s actual condition.

Intervention of 18 December 2024

Rotor shaft machining

Rotor Shaft Machining

As part of a project conducted at a hydroelectric site, an intervention was carried out on the rotor shaft of a generating unit. The objective was to restore a functional surface through a series of coordinated operations, including machining, material build-up, and finishing.

The operation followed several key stages:

  • Initial machining of the affected bearing surface, to prepare it for corrective treatment.

  • Copper build-up, performed by the client, to locally restore material on the functional zone.

  • Final finishing machining, to achieve the required dimensions and tolerances, with precision adapted to the interface specifications.

The operations were performed using an orbital machining system mounted on a dedicated support, with alignment carried out using a laser tracker to ensure precise positioning relative to the shaft axis. The entire intervention took place in a secured environment, with specific arrangements to ensure equipment stability and operator safety.

This type of service illustrates our ability to carry out geometric rehabilitation operations under real-world conditions, meeting high technical standards and contributing to the reliability of critical hydromechanical components.

December 2024

Destruction axe Safran

Destruction axe Safran

🚀 Mission accomplished! 🚀
 
⚙️Destruction of a Safran Ø430 axle with a length of 887 mm, successfully completed. Thanks to the customer for their trust and to the technicians for their precision and efficiency, guaranteeing an intervention in compliance with safety standards.
 
Together, we continue to meet challenges with passion and expertise💪✨
 
Measurement of crankshaft line and crankshaft

Metrological Inspection of a Crankshaft Line and Crankshaft 

A metrology operation was carried out on the crankshaft line and the piston compressor crankshaft, as part of a high-precision geometric inspection. The intervention was performed directly on-site, with the objective of verifying the dimensional conformity of the mechanical components prior to commissioning or reassembly.

Measurements were taken using a laser tracker, enabling detailed analysis of surface conditions, support geometry, and overall shaft alignment. The campaign covered all bearings along the line, with multiple measurement series to validate result stability.

The crankshaft was also thoroughly inspected, including journals and crankpins, to ensure proper integration within the overall assembly and compliance with design tolerances.

All scheduled measurements were successfully completed, validating the functional geometry of the inspected components and confirming their compliance with project specifications.

Intervention of 20 November 2024

Hot tap DN350 on DN500 header

DN350 Hot Tap on DN500 Potable Water Header

Our teams carried out a DN350 PN10 hot tap on a DN500 potable water header, with no service interruption.

Following the installation by the client of a welded DN350 flange connection and a full-bore valve, we proceeded with the hot tapping operations under pressure.

The tapping machine was mounted onto the valve and subjected to a nitrogen tightness test to ensure full safety before drilling. The cut, with a diameter of 324 mm, was performed with precision, and the coupon was returned to the client at the end of the intervention.

In the case of rolled or spiral-welded headers, an internal reinforcement is systematically installed to prevent any equipment blockage and ensure safe execution.

This operation highlights our expertise in large-diameter live tapping, combining technical precision, safety, and compliance with sanitary standards for potable water networks.

Intervention du 22 octobre 2024

Measurement elbow and wheel kaplan

Geometric Measurement of a Hydraulic Elbow and Kaplan Runner

A metrology inspection was carried out on an assembly consisting of a hydraulic elbow and a Kaplan runner, in accordance with the specifications of an established inspection procedure. The operation was conducted both on-site and in the workshop, with measurements taken at various stages of the process, including phases before and after the removal of certain components.

The inspections focused on several key elements: runner diameter, axial position of the blades, perpendicularity of the elbow, and various internal dimensions. A complete survey of the bearing was also performed, with particular attention paid to its centering and perpendicularity.

Additional measurements were taken on an old runner shroud, whose surface condition imposed certain limitations on the analysis. A comparison with the 3D model made it possible to visually identify deviations from the theoretical geometry, particularly in areas with excess material or recesses.

All points outlined in the inspection plan were covered, enabling the establishment of a comprehensive dimensional assessment of the equipment for operational use or future technical interventions.

Intervention of 16 October 2024

Restoration of a Turbo Food Pump

Restoration of a Turbo Food Pump

🔧 Emergency Response at TACQUET INDUSTRIES ⚙️

At the beginning of 2024, in the middle of the winter season, TACQUET INDUSTRIES responds to an urgent call for the restoration of a Turbo Food Pump. This critical situation impacts the operator’s electricity production, which is only stabilized at 47% of capacity.
📉 The strategic and financial stakes are high!

🚀 An expert team is immediately deployed to the site. What’s their mission? Assess the means needed to restore this vital equipment. In no time, a thorough study confirms the procedure and establishes a provisional schedule.

OBJECTIVES
– Dimensional and geometric controls of the upper and lower body combining sophisticated metrology «SCAN 3D & TRACKER LASER» as well as conventional
– Destruction of damaged rushes
– Mechanical crimping of new reeds
– Recovery of the pitting and sealing ranges of these reeds
– Dimensional and geometric checks for acceptance

Days later, our teams start construction 👷
Two machines and a staff of ten technicians are deployed to optimize response time. The checks and analyses are carried out before the first machining operations begin.

💪 The flexibility of our design office, workshop and stakeholders has made it possible to achieve this mission successfully, while respecting our client’s tight schedule.

TACQUET INDUSTRIES, always at your service, even in the most critical moments ! 🚀🔧

LinkedIn Link

Alignment control 2 bronze bearings

Metrological Inspection of a Pump Shaft Line

A metrological inspection was carried out on a pump shaft line as part of an on-site technical assessment. The purpose of the intervention was to verify the alignment and geometry of the bearings, both in their operational position and after disassembly.

Measurements were performed using a high-precision laser tracker, enabling a detailed analysis of the structure and its mechanical interfaces. The study focused on rotational axes and support surfaces, taking into account the specific mounting configurations.

All measurements defined in the scope of the mission were successfully completed, allowing for validation of the installation’s geometry and confirmation of its expected behavior under real operating conditions.

LinkedIn

Intervention of 9 October 2024

Control on Shaft G2

Geometric Inspection of a Shaft at a Hydroelectric Site

A measurement campaign was conducted on a drive shaft as part of an on-site intervention at a hydroelectric facility. The objective was to inspect its position as well as that of several nearby reference elements, such as flats and locating spheres.

The inspection was carried out using a high-precision laser tracker, enabling the acquisition of three-dimensional geometric data directly under operational conditions. All measurements were adjusted to a standard reference temperature to ensure accuracy and reliability.

This operation made it possible to precisely determine the position and orientation of the shaft, while also establishing its relative distances to peripheral reference points. The recorded geometric configuration can serve as a baseline for future adjustments or as part of ongoing dimensional monitoring of the installation.

All elements defined in the scope of the mission were measured in accordance with expectations, ensuring full traceability of the system’s geometry.

Intervention of 8 October 2024

Geometric control of a secondary shaft

Geometric Inspection and Machining of a Shaft

A series of metrology operations was carried out on a crusher shaft, as part of a full inspection and follow-up process before and after corrective machining. These operations were conducted on-site, with the aim of recording the shaft’s initial geometric condition, performing targeted machining, and validating the final dimensions.

Measurements were conducted using a laser tracker, based on a reference system adapted to the shaft’s cylindrical geometry. Thermal conditions were taken into account, with value corrections applied to a standard reference temperature. A specialized metrology software was used to guide the measurement process and optimize data processing.

The intervention included several key stages:

  • Initial inspection of the shaft cylinders, distinguishing between previously machined and raw areas,

  • Machining setup, including the installation of a support ring for machine guides,

  • Orbital machining of the targeted surface,

  • And finally, a geometric validation check post-machining.

This comprehensive approach ensured restoration in compliance with specifications, providing rigorous dimensional traceability throughout all stages of the process—before, during, and after the intervention.

Intervention of 31 August 2024

Control tubular bundles

Comparative Inspection of Two Mechanical Assemblies

A metrology inspection was carried out on two mechanical assemblies, one original and one newly manufactured, with the goal of performing a comparative dimensional analysis. The purpose of this operation was to verify the geometric conformity of the new component in relation to the original part.

Measurements were conducted on-site using a laser tracker, with both global and local reference frames established. This approach enabled precise analysis of the overall structure of the parts, as well as the positioning of key connection elements such as flanges and tubes.

The analysis revealed some geometric differences between the two assemblies, particularly in the relative positioning of the flanges and the overall length of the unit. These variations were interpreted in the context of the expected tolerances and the functional fit within the assembly environment.

The overall inspection confirmed the geometric compatibility of the new assembly, ensuring its proper integration into the designated installation.

Intervention of 27 August 2024

Hot Tapping on Ammonia Water Networks

Execution of 10 Hot Taps on an Ammonia Water Network

As part of a large-scale technical operation, our teams carried out 10 hot taps on an ammonia water network, on headers ranging from DN200 to DN500.
The entire operation was conducted in a demanding environment—under pressure and at controlled temperature—with a high level of precision and safety.

We provided all fittings, including calculation notes, NDT inspections, gaskets, and bolting, in full compliance with the client’s technical specifications.

Hot taps were distributed as follows:

• 2 DN200 taps on a DN200 header
• 2 DN300 taps on a DN300 header
• 2 DN300 taps on a DN400 header
• 4 DN350 taps on a DN500 header

Each tap was preceded by a nitrogen tightness test to ensure system integrity. Our hot tapping machines were then mounted on full-bore valves to perform pressure drilling in a fully controlled manner.

This operation involved access constraints, heavy handling, and a sensitive environment (ammonia water at 68–75°C under 4 to 6.5 bar), and highlights our ability to efficiently operate on complex industrial installations, while meeting the highest technical and safety standards.

26 august 2024

Geometrical control and adjustment of plates

Geometric Inspection and Adjustment of Mounting Plates

As part of an on-site intervention, a complete metrological inspection was carried out on two flanges of a gearbox (alternator side and turbine side) within the industrial environment of the Veolia Valbom unit in Bègles.

The objective of this operation was to check the flatness deviations of the flanges in their original position, record their altitudes, and perform the necessary adjustments through machining. The intervention took place in several phases: initial measurements, mechanical adjustment phase (using a milling arm), and final inspections after machining.

The measurements were carried out using a high-precision laser tracker, with corrections applied to account for the site’s thermal conditions. The surfaces were inspected according to a defined reference frame, ensuring consistency across all measurements.

Following the analysis and adjustment phases, the required values were provided to the machining teams, who made the necessary adjustments in accordance with the specified requirements. The geometry of the components was re-verified after the intervention, confirming compliance with expectations.

This type of service is part of a reliability approach for mechanical interfaces, ensuring precise assemblies optimized for operational performance.

Intervention of 22 August 2024

Rotor control

Adjustment and Geometric Inspection of Rotor

A metrology inspection was carried out on the rotor as part of an on-site geometric alignment procedure. The main objective was to check the key dimensions of the assembly and verify the alignment of the poles.

The measurements were performed using a laser tracker, with a reference frame constructed around the axis of rotation, using the shaft journal as the origin. This reference system enabled precise analysis of the rotor’s geometric characteristics, including profiles, alignments, and the relationships between various sections.

Each pole was inspected at three different heights to assess the consistency of their positioning and to validate the uniformity of the radii. This work ensured precise adjustment of the assembly in line with the installation’s requirements.

The inspections confirmed the geometric compliance of the equipment. As a result, the rotor was successfully aligned and finalized under optimal conditions at the end of the intervention.

Intervention of August 2, 2024

Geometric Inspection of the Lower Base

Geometric Inspection of the Lower Base

A metrology inspection was carried out on the lower base of group G2, which is currently being machined. The main objective was to check the geometry of critical components, particularly the labyrinths and the stay vane housings, and to compare these measurements with those of the upper base.

The measurements were taken using a laser tracker, with the reference frame aligned to the points provided by the client. All data was corrected to a reference temperature of 20°C. Despite certain constraints related to the support of the part, satisfactory measurement accuracy was achieved.

The middle and lower labyrinths were measured in detail, revealing cylindricity deviations of 0.043 mm and 0.059 mm, respectively. The 24 stay vane housings on the lower base were also measured, and their positions were compared to those previously measured on the upper base.

The comparative analysis showed minor deviations, both radially and tangentially, ensuring good alignment between the two bases, which is essential for optimal stay vane performance.

All required points were successfully measured, and the data was integrated into the machine coordinate system of the group, in accordance with the client’s specifications.

Intervention of 15 July 2024

Machining of two crusher shafts

Machining of Two Crusher Shafts

As part of a refurbishment operation, two 900 mm-long transmission shafts underwent precision machining, with a clear objective: to correct out-of-roundness and improve surface finish in order to meet regulatory compliance requirements.

The operation began with controlled grinding of the shaft surfaces, originally at a diameter of Ø419 mm, to achieve a final diameter of Ø416 mm. This process ensured a compliant surface, ready for subsequent babbitt (white metal) lining in accordance with the manufacturer’s specified tolerances.

Following the machining operations, a comprehensive dimensional inspection was carried out using a laser tracker, enabling precise verification of geometries and the adjustment of rings on one of the shafts. A detailed inspection report was prepared to provide the necessary data for the continuation of the babbitt fitting process.

This service highlights the importance of a rigorous sequence of machining and metrology operations, ensuring the functional quality of critical mechanical components before their return to service.

June 2024